Project Info
Description:
New electrical power substation
Type:
COMPREHENSIVE DEVELOPMENT PLAN
Parcel Info
City/State/Zip:
ROANOKE, VA, 24014
Zoning:
I-1: Light Industrial
There are currently no inspections on this record.
|
APPLICATION REVIEW | Adrian Gilbert | APPROVED | 2/17/2023 | 2/17/2023 | 2/21/2023 |
More Info
|
BONDS AND AGREEMENTS | AARON CYPHER | RESUBMISSION REQUIRED | 2/17/2023 | 3/10/2023 | 3/3/2023 |
More Info
|
BUILDING | Tommy Hahn | APPROVED | 2/17/2023 | 2/28/2023 | 3/3/2023 |
More Info
|
COMPLETENESS– CP/SSP | Adrian Gilbert | APPROVED | 2/17/2023 | 2/17/2023 | 2/22/2023 |
More Info
|
DEVELOPMENT | AARON CYPHER | RESUBMISSION REQUIRED | 2/17/2023 | 3/10/2023 | 3/7/2023 |
More Info
|
E AND S OR ROW COST ESTIMATE | AARON CYPHER | RESUBMISSION REQUIRED | 2/17/2023 | 3/10/2023 | 3/3/2023 |
More Info
|
FIRE | Ronnie Campbell | APPROVED | 2/17/2023 | 2/21/2023 | 3/3/2023 |
More Info
|
INITIAL SITE REVIEW | Adrian Gilbert | APPROVED | 2/17/2023 | 2/21/2023 | 3/3/2023 |
More Info
|
RIGHT-OF-WAY IMPROVEMENTS | Adrian Gilbert | RESUBMISSION REQUIRED | 2/17/2023 | 2/23/2023 | 3/3/2023 |
More Info
|
STORMWATER UTILITY | JOSEPH JUDY | APPROVED | 2/17/2023 | 2/21/2023 | 3/3/2023 |
More Info
|
TRAFFIC | IAN COFFEY | RESUBMISSION REQUIRED | 2/17/2023 | 2/22/2023 | 3/3/2023 |
More Info
|
WESTERN VIRGINIA WATER AUTHORITY | MARGARET PEARSON | APPROVED | 2/17/2023 | 3/3/2023 | 3/3/2023 |
More Info
|
ZONING | BRITTANY GARDNER | RESUBMISSION REQUIRED | 2/17/2023 | 3/3/2023 | 3/3/2023 |
More Info
|
ZONING FLOODPLAIN REVIEW | BRITTANY GARDNER | RESUBMISSION REQUIRED | 2/17/2023 | 3/3/2023 | 3/4/2023 |
More Info
|
BONDS AND AGREEMENTS | AARON CYPHER | RESUBMISSION REQUIRED | 9/13/2023 | 9/25/2023 | 9/21/2023 |
More Info
|
DEVELOPMENT | AARON CYPHER | RESUBMISSION REQUIRED | 9/14/2023 | 9/25/2023 | 9/21/2023 |
More Info
|
E AND S OR ROW COST ESTIMATE | AARON CYPHER | APPROVED | 9/14/2023 | 9/25/2023 | 9/21/2023 |
More Info
|
RIGHT-OF-WAY IMPROVEMENTS | Adrian Gilbert | APPROVED | 9/14/2023 | 9/22/2023 | 9/21/2023 |
More Info
|
TRAFFIC | IAN COFFEY | APPROVED | 9/14/2023 | 9/15/2023 | 9/21/2023 |
More Info
|
ZONING | BRITTANY GARDNER | RESUBMISSION REQUIRED | 9/14/2023 | 9/22/2023 | 9/21/2023 |
More Info
|
ZONING FLOODPLAIN REVIEW | BRITTANY GARDNER | RESUBMISSION REQUIRED | 9/14/2023 | 9/22/2023 | 9/21/2023 |
More Info
|
BONDS AND AGREEMENTS | AARON CYPHER | RESUBMISSION REQUIRED | 10/31/2023 | 11/7/2023 | 11/7/2023 |
More Info
|
DEVELOPMENT | AARON CYPHER | RESUBMISSION REQUIRED | 10/31/2023 | 11/7/2023 | 11/7/2023 |
More Info
|
ZONING | BRITTANY GARDNER | APPROVED | 10/31/2023 | 11/9/2023 | 11/7/2023 |
More Info
|
ZONING FLOODPLAIN REVIEW | BRITTANY GARDNER | APPROVED | 10/31/2023 | 11/9/2023 | 11/7/2023 |
More Info
|
BONDS AND AGREEMENTS | AARON CYPHER | APPROVED | 12/6/2023 | 12/6/2023 | 12/6/2023 |
More Info
|
DEVELOPMENT | AARON CYPHER | APPROVED | 12/6/2023 | 12/6/2023 | 12/8/2023 |
More Info
|