Description:
Carilion Hospital Expansion enabling Project # 1A
Type:
COMPREHENSIVE DEVELOPMENT PLAN
Subtype:
GRADING, E&S, LARGE SCALE
Parcel Info
Zoning:
INPUD: Institutional Planned U
There are currently no inspections on this record.
|
APPLICATION REVIEW | | APPROVED | 12/16/2019 | 12/16/2019 | 12/17/2019 |
More Info
|
COMPLETENESS– CP/SSP | Adrian Gilbert | APPROVED | 12/16/2019 | 12/17/2019 | 12/18/2019 |
More Info
|
ZONING CONDITIONS OR PUD | Katharine Gray | APPROVED | 12/16/2019 | 12/20/2019 | 12/23/2019 |
More Info
|
ZONING FLOODPLAIN REVIEW | Phillip Moore | APPROVED | 12/16/2019 | 1/8/2020 | 12/31/2019 |
More Info
|
BONDS AND AGREEMENTS | Ken Richardson | RESUBMISSION REQUIRED | 12/17/2019 | 1/7/2020 | 1/6/2020 |
More Info
|
BUILDING | Tommy Hahn | APPROVED | 12/17/2019 | 1/7/2020 | 1/6/2020 |
More Info
|
DEVELOPMENT | Ken Richardson | RESUBMISSION REQUIRED | 12/17/2019 | 1/7/2020 | 1/6/2020 |
More Info
|
E AND S OR ROW COST ESTIMATE | Ken Richardson | RESUBMISSION REQUIRED | 12/17/2019 | 1/7/2020 | 1/6/2020 |
More Info
|
ECONOMIC DEVELOPMENT | Robert Ledger | APPROVED | 12/17/2019 | 12/20/2019 | 1/6/2020 |
More Info
|
ENGINEERING - PLAN | Luke Pugh | APPROVED | 12/17/2019 | 12/24/2019 | 1/6/2020 |
More Info
|
FIRE | Ronnie Campbell | APPROVED | 12/17/2019 | 1/6/2020 | 1/6/2020 |
More Info
|
RIGHT-OF-WAY IMPROVEMENTS | Ian Shaw | APPROVED | 12/17/2019 | 1/10/2020 | 1/6/2020 |
More Info
|
STORMWATER UTILITY | JOSEPH JUDY | APPROVED | 12/17/2019 | 12/17/2019 | 1/6/2020 |
More Info
|
TRAFFIC | IAN COFFEY | RESUBMISSION REQUIRED | 12/17/2019 | 1/2/2020 | 1/6/2020 |
More Info
|
ZONING | Katharine Gray | APPROVED | 12/17/2019 | 12/20/2019 | 1/6/2020 |
More Info
|
WESTERN VIRGINIA WATER AUTHORITY | AARON SHEARER | APPROVED WITH CONDITION | 1/3/2020 | 1/3/2020 | 1/6/2020 |
More Info
|
BONDS AND AGREEMENTS | Ken Richardson | RESUBMISSION REQUIRED | 1/27/2020 | 2/3/2020 | 2/3/2020 |
More Info
|
DEVELOPMENT | Ken Richardson | RESUBMISSION REQUIRED | 1/27/2020 | 2/3/2020 | 2/3/2020 |
More Info
|
E AND S OR ROW COST ESTIMATE | Ken Richardson | RESUBMISSION REQUIRED | 1/27/2020 | 2/3/2020 | 2/3/2020 |
More Info
|
TRAFFIC | IAN COFFEY | APPROVED | 1/27/2020 | 1/27/2020 | 2/3/2020 |
More Info
|
E AND S OR ROW COST ESTIMATE | Ken Richardson | APPROVED | 2/24/2020 | 2/25/2020 | 2/24/2020 |
More Info
|
BONDS AND AGREEMENTS | Ken Richardson | APPROVED | 4/6/2020 | 4/8/2020 | 4/7/2020 |
More Info
|
DEVELOPMENT | Ken Richardson | RESUBMISSION REQUIRED | 6/9/2020 | 6/11/2020 | 6/11/2020 |
More Info
|
ZONING | Katharine Gray | APPROVED | 6/9/2020 | 6/10/2020 | 6/11/2020 |
More Info
|
STORMWATER UTILITY | JOSEPH JUDY | RESUBMISSION REQUIRED | 6/10/2020 | 6/10/2020 | 6/11/2020 |
More Info
|
DEVELOPMENT | Ken Richardson | APPROVED | 6/11/2020 | 6/12/2020 | 6/12/2020 |
More Info
|
STORMWATER UTILITY | Ken Richardson | APPROVED WITH CONDITION | 6/11/2020 | 6/16/2020 | 6/12/2020 |
More Info
|
DEVELOPMENT AS BUILT | Ken Richardson | APPROVED | 2/24/2021 | 2/25/2021 | 2/26/2021 |
More Info
|