Notes:
9/24/2025 4:50:23 PM
Replace the existing 60A bubble meter socket with a new 200A/200A meter/main combo in the existing meter socket location. Replace the existing service entrance cable with a new 4/0 AL SEU cable. Replace the existing indoor fused panels with a new 100A sub panel. Run new 4 wire SER cable to the new indoor panel. Feed the indoor panel from a 100A breaker in the new meter/main. Install two ground rods 6’ft apart as a new grounding electrode for the home. Install an ISG bridge and surge protection device at the new meter/main. PV circuit to interconnect via load side breaker in the new meter/main.